R.C.C 1:2:4 materials required per m3



D2
R.C.C 1:2:4 materials required per m3
Cement           =          ?
Sand                =          ?
20mm C.A       =          ?
It’s Very simple way to find out our Answers
Ok
Add (+) our ratio total is         = (1+2+4)         =          7
20mm(4)
                        =          (4/7)x1.56x1    =0.891 m3
Sand(2)
                        =          (2/7)x1.56x1    =0.4457 m3
Cement(1)
                        =(1/7)x1.56x1440x1    = 320.914 kg/m3
                                    (1 bag=50kg)so  (320.914/50)= 6.418 bag

SAME AS ON OTHER RATIO JUST CHANGE THE VALUES ONLY