R.C.C 1:2:4 materials required per m3
D2
R.C.C 1:2:4 materials required per m3
Cement = ?
Sand = ?
20mm C.A = ?
It’s Very
simple way to find out our Answers
Ok
Add (+) our
ratio total is = (1+2+4) = 7
20mm(4)
= (4/7)x1.56x1 =0.891 m3
Sand(2)
= (2/7)x1.56x1 =0.4457 m3
Cement(1)
=(1/7)x1.56x1440x1 = 320.914 kg/m3
(1
bag=50kg)so (320.914/50)= 6.418 bag
SAME AS ON OTHER RATIO JUST CHANGE THE VALUES ONLY